Unlike the Production Schedule Report, which focuses on planned and actual production quantities across phases, the Current Timeline Report provides a timeline-based representation of job-order progress and production activity over a selected reporting period.
The report can be accessed through:
Production → Reports → Current Timeline
The report is used to monitor job-order timelines, analyse production progress and identify scheduling delays within active manufacturing operations.
It is commonly used by:
Production planners
Workshop supervisors
Factory managers
Operations teams
Management personnel
The report is especially useful for monitoring production status, identifying lagging job orders and evaluating schedule adherence across manufacturing workflows.
The report interface contains:
Organisation selection
Production-type filtering
Workshop filtering
Sorting controls
Date-range selection
Timeline-based production grid
The ENTIRE ORGANIZATION selector allows users to generate timeline views across accessible organisations, companies, factories or branches.
The Type selector supports filtering based on job-order categories and production types. Available options depend on the organisation's production configuration and may include production orders, sampling orders, internal consumption orders, job work orders and other organisation-specific production types.
The Workshop selector allows users to analyse timelines for specific workshops, departments or production units. Available workshops depend on the organisation’s production structure.
The Sort By selector supports multiple timeline-analysis perspectives including:
Job Number
Created Date
Start Date
Target Date
Closing Date
Description
Status
Total Cost
Total Value
The report also supports configurable date-range selection for reviewing both historical and future production schedules.
The report is displayed as a timeline-based production schedule grid.
Each row represents a job order while each column represents a reporting date within the selected timeline period.
Depending on system configuration, each job-order row may display:
Job Order Number
Customer Information
Production Description
Timeline Activity Indicators
Planned Production Periods
Actual Production Activity
Schedule Status Indicators
This structure allows organisations to quickly evaluate production progress across multiple job orders simultaneously.
The report uses colour-based indicators to visually represent production status and scheduling information.
|
Indicator |
Description |
|
Light Green |
Date falls within the planned production period |
|
Green |
Planned production quantity exists for that date |
|
Dark Green |
Production activity exists for that date (actual production, rejection or wastage) |
|
Red Line |
Lag status; cumulative production is lower than cumulative planned production up to that date |
|
Blue Vertical Line |
Current date reference within the timeline |
Multiple timeline indicators may appear during the same reporting period, allowing users to compare production plans against actual production activity.
The report supports production lag monitoring through visual lag indicators.
A lag condition occurs when cumulative production achieved up to a particular date is lower than cumulative production planned up to the same date.
This allows organisations to quickly identify:
Delayed job orders
Production bottlenecks
Scheduling issues
Manufacturing activities requiring corrective action
Job order numbers displayed within the report are clickable.
Selecting a job order opens the corresponding Job Order record, allowing users to access detailed production, customer, workflow and operational information associated with that order.
This functionality provides direct navigation from production monitoring activities to operational job-order management.
|
Utility |
Description |
|
Production Schedule |
Opens the Production Schedule Report (M102) |
|
Job Orders |
Opens the Job Orders module |
The report supports:
Production timeline monitoring
Job-order progress tracking
Production scheduling visibility
Lag analysis
Workshop-level production monitoring
Active production tracking
Schedule adherence analysis
Displayed information varies depending on the selected filters, workshops, production types and reporting period.
The Current Timeline Report provides a visual production timeline and job-order progress tracking view within TUHUND.
By combining timeline-based scheduling visibility, production activity monitoring, lag detection and direct job-order integration, the report enables organisations to monitor manufacturing progress, identify production delays and evaluate schedule adherence across operational workflows.